Ophel Excavation 2026 (Upper Area)

 

Welcome to the 2026 Ophel Area E excavation—a joint project of Hebrew University and the Armstrong Institute of Biblical Archaeology and partners, directed by Hebrew University professor Yosef Garfinkel.

Area E is a new excavation area in the ongoing Ophel excavations initiated by the late Dr. Eilat Mazar and continued in recent years by Prof. Uzi Leibner and Prof. Orit Peleg-Barkat. It was Dr. Mazar’s dream to excavate Area E. “I’m so anxious to excavate there,” she told our team in 2018. Why was this area so important to Dr. Mazar?

In previous Ophel excavations (2009, 2012, and 2013), Dr. Mazar had uncovered several sensational finds from Jerusalem’s First Temple Period, the time of King Solomon (10th century b.c.e.) through the destruction of the temple in 586 b.c.e. In addition to uncovering extraordinary artifacts, such as the royal seal of King Hezekiah, Dr. Mazar revealed extensive monumental architecture, further attesting to the grandeur of the Judean kingdom. For Dr. Mazar, excavating Area E was the logical (and exciting) next step in further revealing the “monumental royal crescent” of biblical period architecture. Dr. Mazar believed we would discover at least 5 meters (16 feet) of preserved First Temple Period remains, undisturbed even by the Second Temple Period.

Area E

We are thrilled to excavate Area E with Professor Garfinkel, Hebrew University, and other important donors to continue the work of Dr. Mazar, our mentor and friend. Follow closely as we excavate this important area. As always, the most recent updates will be at the top.

Meet the Crew

The Area E volunteers: (back, from left) Lev, Eli, Stephen, Chris, Brent, Micah, Lance, Josiah, Brett and Aubrey; (front, from left) Nicholas, Marcus, Prof. Yosef Garfinkel, Quinn, Hali, Lara, Deepika, Azariah

Area E group picture, Mount of Olives in the background
Aubrey Mercado/AIBA

September 2: Finding a Wall

The crew has accomplished a lot this week. With less than a week and a half left at the site, everyone is working hard to get as much done as possible. We successfully found another wall in our large Byzantine room in square 1—a discovery we were anticipating. We have also continued to find coins in all areas. In the Iron Age section, we found a couple pieces of horse figurines. We also found a Hasmonean slingstone today—time will tell if something is inscribed on it like the one we found in 2023.

September 2: Chris excavates a nicely outlined room in the southern section.
Aubrey Mercado/AIBA
September 2: Hali and Josiah expose remnants of a collapse.
Aubrey Mercado/AIBA
September 2: Deepika, Lara and Stephen excavate the northernmost section.
Aubrey Mercado/AIBA
September 2: Dig director Prof. Yosef Garfinkel wields the pickax in the northern section.
Aubrey Mercado/AIBA
September 2: Lara passes to Azariah in a sharsheret.
Aubrey Mercado/AIBA

September 1: Drawing the Site

The site is rapidly changing. We had dig architect Marcus Edelcopp out today to draw new plans—giving us an updated map to work off of.

September 1: Ahavah videos Professor Garfinkel speaking about the excavation for Hebrew University.
Aubrey Mercado/AIBA
September 1: Marcus measures stones, walls and fill to update his architectural drawings of Area E.
Aubrey Mercado/AIBA
September 1: Quinn wet-sifts Iron Age material from the lower area.
Aubrey Mercado/AIBA
September 1: Micah cleans his locus in the lower area.
Aubrey Mercado/AIBA

August 31: Various Activities

The site was busy today with sifting, cleaning, digging and sharshereting. The crew is making great progress in all areas.

August 31: Quinn and Stephen dry-sift Iron Age material from the lower area.
Aubrey Mercado/AIBA
August 31: Micah creates a “gate” to give access to the outside of the staircase leading down to the lower area.
Aubrey Mercado/AIBA
August 31: Leah, Brett and Azariah excavate the lower area.
Aubrey Mercado/AIBA
August 31: Deepika excavates the corner of a Byzantine wall jutting through the Umayyad wall.
Aubrey Mercado/AIBA
August 31: Lara and Anthony excavate the southernmost locus.
Aubrey Mercado/AIBA
August 31: Quinn passed buckets up to Hali in the easternmost section.
Aubrey Mercado/AIBA
August 31: Stephen cleans a Byzantine mosaic floor.
Aubrey Mercado/AIBA

August 30: Week Four Begins

The week got off to a pleasant start with some light rain this morning—leading to cooler temperatures throughout the day. In the southernmost portion of the upper area, the crew discovered the closing wall of our Byzantine room. In the lower area, we are uncovering a water installation that appears to be a ritual bath. We also discovered the leg of an Iron Age horse figurine.

August 30: Chris and Lara excavate the southernmost section.
Aubrey Mercado/AIBA
August 30: Brent uses the pickax in the fill of the Umayyad wall.
Aubrey Mercado/AIBA
August 30: Hali uses the pickax to dislodge large stones.
Aubrey Mercado/AIBA
August 30: Quinn wet-sifts Iron Age fill.
Aubrey Mercado/AIBA
August 30: Buckets are stacked near the dumpster drop-off, awaiting a new dumpster.
Aubrey Mercado/AIBA
August 30: Area supervisor Brent Nagtegaal points out the Byzantine wall running under the Umayyad wall.
Aubrey Mercado/AIBA

August 27: Sifting

Today, we began dry and wet sifting the soil from one particular locus in the lower area. This area is producing almost exclusively Iron Age pottery. This is an exciting development for the site. We look forward to better understand the First Temple Period in this area.

August 27: Josiah and Hali dry-sift soil from a locus producing mostly Iron Age finds.
Aubrey Mercado/AIBA
August 27: Eli excavates on the northern edge.
Aubrey Mercado/AIBA
August 27: Chris passes up to Stephen in the sharsheret.
Aubrey Mercado/AIBA
August 27: Sharsheret lines form daily on the dig to remove tons (literally) of dirt and rocks.
Aubrey Mercado/AIBA

August 26: An Active Site

August 26: A sharsheret line of most of the volunteers removes soil and rocks from the lower section.
Aubrey Mercado/AIBA
August 26: Brett and Micah construct a platform and staircase down to the lower area.
Aubrey Mercado/AIBA
August 26: Quinn wields a pickax.
Aubrey Mercado/AIBA
August 26: Stephen excavates a collapse in the first square.
Aubrey Mercado/AIBA
August 26: Chris, Lara and Deepika continue going down in the southern section.
Aubrey Mercado/AIBA
August 26: Josiah, Hali and Quinn work to remove modern rocks, soil and debris.
Aubrey Mercado/AIBA
August 26: Azariah removes rocks in a new section abutting the northern end of the Umayyad wall.
Aubrey Mercado/AIBA
August 26: Quinn, Hali and Josiah break up a new section.
Aubrey Mercado/AIBA

August 25: A Conversation With the Director

Today, we posted a Let the Stones Speak interview with excavation director Prof. Yosef Garfinkel. The 15-minute discussion covers how the excavation came about, Professor Garfinkel’s history excavating Jerusalem, as well as why we are hopeful to find significant remains from royal Jerusalem of the First Temple Period.

https://www.youtube.com/watch?v=1D08ZPn70Ao

August 24: Opening New Loci

Since we are discovering more walls and uncovering cleaner archaeological layers, we opened a number of new loci today. We are also better understanding how walls in the upper area may correspond with walls in the lower area. We spent a good portion of the morning cleaning our northernmost square for a picture. We also prepared the area to open a new locus adjacent to this square, which will help us better understand the entire area and give us more context to what we have uncovered thus far.

August 24: Brent and Nick discuss excavating the western corner of the Byzantine room.
Aubrey Mercado/AIBA
August 24: Nick’s son, Cole, carries a stack of buckets.
Aubrey Mercado/AIBA
August 24: Nick’s daughter, Jane, carries a bucket of tools.
Aubrey Mercado/AIBA
August 24: Micah and Azariah excavate along a wall in the lower section.
Aubrey Mercado/AIBA
August 24: Lance and Quinn clean the wall adjoining the Byzantine room as Stephen and Eli clean inside.
Aubrey Mercado/AIBA
August 24: Workers fill the upper area as the workday begins.
Aubrey Mercado/AIBA

August 23: Revealing Walls

More and more walls are being revealed throughout the site. In the lower area, the crew have found more than 20 coins that date the current locus to the end of the first century c.e. and earlier.

August 23: Area supervisor Brent excavates a doorway abutting the Umayyad wall in the northernmost upper area.
Aubrey Mercado/AIBA
August 23: Stephen and Eli discuss a find in the middle section of Area E, where they uncovered a Byzantine mosaic floor.
Aubrey Mercado/AIBA
August 23: Excavators in the southernmost section begin to expose the tops of walls.
Aubrey Mercado/AIBA
August 23: Diggers excavate the lower portion of Area E.
Aubrey Mercado/AIBA

August 20: Closing the Week

We wrapped up our second week with great progress in all the areas. We excavated within the large Umayyad wall and found a number of coins that will help date the area. Excavations within the northernmost square also produced what appears to be a doorway—giving the crew something to look forward to investigating on Sunday.

August 20: Kathy cleans in the upper area.
Aubrey Mercado/AIBA
August 20: Hali cleans the rock fill in preparation for a documentary photo.
Aubrey Mercado/AIBA
August 20: Stephen cleans along the Umayyad wall.
Aubrey Mercado/AIBA
August 20: Chris, Josiah and Lara excavate.
Aubrey Mercado/AIBA

August 19: Removing the Ballista Stone

Four hundred thirty-eight—that’s how many buckets we emptied into the dumpster in one of our sharsherets. We average between 350 to 450 buckets for each sharsheret and do about three sharsherets per day. In the three upper squares, we are almost completely in clean archaeological contexts with no plastic or modern fill. We reached a mosaic floor abutting one of our walls that cuts through the squares. In the lower area, the crew took down the middle Roman Period wall. A nice ballista stone was sitting within this wall. We’ve had our eyes on this stone since our 2023 excavations. Today, Micah dislodged it, and we carried it up to the office for cleaning and registering.

August 19: Eli discovered a Byzantine mosaic floor in the upper area.
Aubrey Mercado/AIBA
August 19: Micah dislodges the ballista stone.
Aubrey Mercado/AIBA
August 19: Micah loosens dirt around a ballista stone used as part of a wall in the lower area.
Aubrey Mercado/AIBA
August 19: Micah and Azariah set up the lata to its highest height to get an elevation reading on a coin.
Aubrey Mercado/AIBA
August 19: Josiah uses the metal detector in the lower area.
Aubrey Mercado/AIBA
August 19: All volunteers fill the sharsheret as the sun rises over the Mount of Olives.
Aubrey Mercado/AIBA

August 18: Dating the Wall

We had a successful day at the dig site. The large Umayyad wall is one of the most prominent features of our area. Today, we found a coin abutting the wall in a clean archaeological context. This will allow us to more accurately date the wall. We are also getting a decent amount of coins from our lower area. One of the best finds of the day, in fact, was from the lower area: Azariah discovered a Second Temple Period soffit—very similar to the one we discovered on the Ophel in 2023.

August 18: Brett and Michael check out the writing on the coin.
Aubrey Mercado/AIBA
August 18: Michael, son of the area supervisor Brent, holds up a coin discovered in the Umayyad wall.
Aubrey Mercado/AIBA
August 18: Josiah uses the metal detector in the Umayyad wall between the upper and lower sections of Area E.
Aubrey Mercado/AIBA
August 18: Azariah holds a Herodian soffit she discovered in secondary use in the wall in the lower area.
Aubrey Mercado/AIBA

August 17: Reaching Clean Archaeology

Today, we finally reached a clean layer within one of the squares—no trash, no large stones, and different color earth. We also began excavating the fill within the large Umayyad wall in preparation of removing a course of stones. The crew is making great progess; the area is nearly unrecognizable from what it was this time last week.

August 17: Professor Garfinkel holds up a plumb bob.
Aubrey Mercado/AIBA
August 17: Brett excavates the fill in the Umayyad wall dividing the upper and lower areas.
Aubrey Mercado/AIBA
August 17: Azariah cleans in the lower area.
Aubrey Mercado/AIBA
August 17: The upper area makes headway in removing modern fill.
Aubrey Mercado/AIBA
August 17: Lara celebrates the removal of gnarly tree roots from her section.
Aubrey Mercado/AIBA
August 17: Deepika excavates along the wall between the upper area’s squares.
Aubrey Mercado/AIBA
August 17: Eli continues removing modern fill from the upper area.
Aubrey Mercado/AIBA
August 17: Lev excavates the lower area.
Aubrey Mercado/AIBA

August 16: Record-breaking Rainfall

On the afternoon of August 15, Jerusalem experienced a once-in-a-century event: record-breaking rainfall in August. This made for cooler temperatures and less dust at the dig site the next morning, getting our week off to a great start. After resetting the shades, everyone got to work in the various loci. We’re still encountering trash and a lot of rocks in the three upper squares. Despite the large stones, we’re still able to work through the fill quickly. We’re hoping to reach a clean archaeological layer soon.

August 16: Workers in the upper area keep plowing through the modern fill.
Aubrey Mercado/AIBA
August 16: Professor Garfinkel and area supervisor Brent Nagtegaal discuss the progress.
Aubrey Mercado/AIBA
August 16: Brent hammers a chunk off a large boulder.
Aubrey Mercado/AIBA
August 16: Assistant supervisor Nicholas Irwin works at the area desk with the Mount of Olives as his backdrop.
Aubrey Mercado/AIBA
August 16: Chris holds a glass Coke bottle pulled from the fill.
Aubrey Mercado/AIBA

August 13: Excavating in the Lower Area

Some of the crew were able to excavate in the lower area, working on what is believed to be a Herodian Period water tunnel—what we’re calling Channel A. This channel is interesting because it has a steep incline, dropping relatively sharply over a short distance. We finished off the week sharshereting buckets for 35 minutes (we had a lot of buckets) and packing up the site for the weekend.

August 13: Stephen stacks buckets along the wall outside the upper area square.
Aubrey Mercado/AIBA
August 13: Hali passes a small find to Lance.
Aubrey Mercado/AIBA
August 13: Azariah takes the sledgehammer to the second course of the wall, after Micah took out the first course.
Aubrey Mercado/AIBA
August 13: Esther laughs while washing pottery.
Aubrey Mercado/AIBA
August 13: Micah removes the modern wall in the lower area.
Aubrey Mercado/AIBA
August 13: Brent dusts the wall for a photo.
Aubrey Mercado/AIBA
August 13: Lara accumulates a personal collection of buckets.
Aubrey Mercado/AIBA
August 13: Micah cleans the channel for a photo.
Aubrey Mercado/AIBA

August 12: Working Hard

The crew is working quickly, even with the large amount of stones we are having to remove from the fill. As we would find out, the theme of this week would be removing large stones.

August 12: Josiah holds up the fragment of an oil lamp he found.
Aubrey Mercado/AIBA
August 12: Lance and Micah prepare to lift a boulder out of the square.
Aubrey Mercado/AIBA
August 12: The volunteers form a double sharsheret line to the dumpster.
Aubrey Mercado/AIBA
August 12: Hali and Quinn remove earth from between the stones.
Aubrey Mercado/AIBA
August 12: Azariah and Brett work in the lower section.
Aubrey Mercado/AIBA
August 12: Professor Garfinkel excavates the upper area along the pathway.
Aubrey Mercado/AIBA

August 10: Removing the Fill

Much like yesterday, we continued to work through the modern fill within the area. By the end of the day, we were in a good place to start the next morning by dividing the individual excavation squares and starting proper archaeology.

August 10: Stephen dumps a wheelbarrow full of dirt and rocks into the dumpster.
Aubrey Mercado/AIBA
August 10: The crew of diggers works to get through modern fill so the “archaeology” can begin.
Aubrey Mercado/AIBA
August 10: Josiah carries a stack of buckets down to the excavation area.
Aubrey Mercado/AIBA
August 10: Brett uses the pickax to break up dirt and rocks while Hali uses the turia (hoe) to fill the buckets.
Aubrey Mercado/AIBA
August 10: Lara fills buckets of soil.
Aubrey Mercado/AIBA
August 10: Stephen and Quinn work on the southern edge of Area E.
Aubrey Mercado/AIBA

August 9: Breaking the Surface

After a restful weekend, we were back at the Ophel to continue work in Area E. This area will consist of four excavation squares. Three will be in the upper area—running along the large Ummayad (Muslim Period) wall. The fourth square will be in the lower Area E, which we previously excavated in 2023. Three to four meters below the upper area, the lower area is filled with immediate potential. At the end of the 2023 season, we had possibly reached pre-Herodian Period walls.

In the upper area, we are having to work through an extensive fill layer before reaching proper archaeology. Hopefully one more day of breaking through the fill and then we can set up our squares and begin excavating.

August 9: A mini-sharsharet forms to remove buckets from Area E at the end of the day.
Aubrey Mercado/AIBA
August 9: Director Prof. Yossi Garfinkel and Josiah toss trees into the dumpster.
Aubrey Mercado/AIBA
August 9: Hali works alongside the wall separating upper Area E from lower Area E.
Aubrey Mercado/AIBA
August 9: Area E assistant supervisor Nicholas Irwin and Josiah use large pick-axes to break up dirt.
Aubrey Mercado/AIBA
August 9: Micah guides the motorized mini-dumper (which holds about twice as much as a wheelbarrow) to the dumpster.
Aubrey Mercado/AIBA
August 9: Lance works on the shades over Area E.
Aubrey Mercado/AIBA
August 9: Azariah removes sandbags from lower Area E.
Aubrey Mercado/AIBA
August 9: Stephen cleans the lower area of Area E.
Aubrey Mercado/AIBA
August 9: Deepika dumps soil into a wheelbarrow to haul to the dumpster.
Aubrey Mercado/AIBA
August 9: Area E supervisor Brent Nagtegaal asks for volunteers on the first day of excavation/clean-up.
Aubrey Mercado/AIBA

August 6: Prepping the Area

With most of the crew required at the site to finish work in Areas D and D1, we took the opportunity to do some prep work in Area E, setting up shades and removing vegetation and trash. This will allow us to jump right in on Sunday, removing the fill layer and beginning excavation.

August 6: Brent chats with Quinn as they prepare Area E for excavation.
Nicholas Irwin/AIBA
August 6: Hali: What’s wrong with this picture?
Nicholas Irwin/AIBA
August 6: Brent removes a tree in Area E.
Nicholas Irwin/AIBA